Short answer By sea, plan 16 to 19 days to the US West Coast and 26 to 40 days to New York, port to port. North Europe averages 38 days and Valencia 42 days. Door to door, add one to three weeks. Air takes 4 to 7 days and express 1 to 3 business days.
Key takeaways
US West Coast is the fastest sea lane: Shanghai to Long Beach averaged 16 days in ShipsGo tracking, 15/05/2026 to 15/11/2026.
Europe is still slow: Yantian to Rotterdam averaged 38 days, with carriers ranging from 34 to 48 days.
Door to door adds weeks: one example lane goes from 16 days port to port to about 30 days door to door (indicative).
Only 50.60% of ships arrived on time in September 2026, and late ships were 6.65 days late on average (Sea-Intelligence).
Chinese New Year 2027 runs 05/02 to 13/02/2027: plan your last pre-holiday sailing now, not in January.
Some links on this page are affiliate links. We may earn a commission at no extra cost to you. It never changes our ranking. How we make money
Your supplier says the goods are ready next week. Your customer wants them on the shelf in six weeks. The real question is the shipping time from China to your door, not the number on a forwarder's website.
Most pages quote one range, such as "20 to 40 days by sea". That hides three things: the lane, the gap between port-to-port and door-to-door, and the 2026 disruptions. This guide gives measured transit days by lane, the extra days on land, and a method to plan order dates backwards.
Shipping time from China at a glance: sea, air, express and rail
The table below gives the typical time for each mode. It shows whether the figure is port to port or door to door. Always ask which one a quote means, because the gap can be two weeks or more.
| Mode and lane | Typical time | Basis | Source type |
|---|---|---|---|
| Sea, Shanghai to Long Beach | 16 days average (14-25 by carrier) | Port to port | Measured containers |
| Sea, Shanghai to New York | 26-40 days | Port to port | Carrier schedules |
| Sea, Yantian to Rotterdam | 38 days average (34-48) | Port to port | Measured containers |
| Sea, Shanghai to Valencia | 42 days average | Port to port | Measured containers |
| Sea, South China to Morocco, Tunisia, Egypt | 22-40 days | Port to port | Forwarder ranges (indicative) |
| Sea FCL, Shanghai to Los Angeles | 20-35 days | Door to door | Forwarder (Ship4wd) |
| Rail, China to Europe | 14-25 days | Terminal to terminal | Forwarder (Forto) |
| Air freight, China to Europe | 4-7 days | Airport based | Forwarder (Forto) |
| Express, FedEx International Priority | 1-3 business days | Door to door | Carrier (FedEx) |
"Measured" means ShipsGo averages of real containers, loading to discharge, tracked from 15/05/2026 to 15/11/2026. "Carrier schedules" are sailings listed by Yunxi Logistics on 16/11/2026. Forwarder ranges are indicative.
For cost rather than days, see our sea freight vs air freight cost comparison.
Sea freight transit times from China by lane
Sea time depends on the origin port, on direct or transshipped service, and on the route around the Red Sea or Hormuz.
1. US West Coast: about 12 to 23 days
This is the shortest major lane. ShipsGo measured 16 days on average from Shanghai to Long Beach, with carriers ranging from 14 to 25 days. Yantian to Long Beach averaged 19 days. Shanghai to Los Angeles averaged 19 days, with 95.00% of boxes sailing direct.
The fastest published sailings are shorter. In the 16/11/2026 schedule, Matson and CMA CGM listed 12 days from Ningbo to Long Beach and Los Angeles. Yantian to Los Angeles ran from 14 to 22 days, depending on the carrier.
Here is what this means in practice: a "12-day" quote is one fast carrier, not the lane average.
2. US East and Gulf Coast: about 26 to 41 days
All-water services to New York, Savannah and Houston go through the Panama Canal or the Suez Canal. Published schedules showed 26 to 40 days from Shanghai to New York and 31 to 41 days from Yantian. Yantian to Savannah ran 30 to 36 days.
Some importers land at Los Angeles and rail the box inland. The same schedule shows Chicago reached via Los Angeles plus 10 to 13 days by rail.
3. North Europe: about 34 to 48 days
ShipsGo measured 38 days on average from Yantian to Rotterdam, with carriers ranging from 34 to 48 days. The wide range reflects routing. Some services already use the Suez Canal again, while others still sail around the Cape of Good Hope.
Forto, a digital forwarder, put China-Europe sea transit at "often exceeding 30-45 days at present" on 07/10/2026. If you need Europe faster, compare China-Europe rail freight, which runs about 14 to 25 days.
4. Mediterranean and Egypt: about 38 to 45 days
Shanghai to Valencia averaged 42 days in the ShipsGo data, and Shanghai to Istanbul (Ambarli) averaged 45 days. Shanghai to Port Said in Egypt averaged 38 days. Note that 83.00% of those Port Said boxes changed ship on the way.
5. North Africa: Morocco, Tunisia and Egypt (indicative)
Few lanes to North Africa have public measured data. Goodhope Freight, a Shenzhen forwarder, gives indicative port-to-port ranges from South China in a log dated 23/09/2026. It quotes 22 to 34 days to Egypt, 26 to 38 days to Tunisia and 28 to 40 days to Morocco.
It adds 3 to 7 days for cargo loaded in North China. It also says direct services beat transshipment routings by one to two weeks. Tanger Med, Casablanca and Radès are often served by feeder ships from Mediterranean hubs, so ask about the hub and the feeder.
6. Gulf: UAE, Saudi Arabia and the Hormuz problem
Goodhope gives 15 to 25 days from South China to the UAE, port to port. That range is indicative, from the same forwarder log. Since 28/02/2026, ships bound for ports inside the Strait of Hormuz have faced serious disruption, covered in the delays section below.
Jeddah, Khor Fakkan and Fujairah avoid the Hormuz crossing, but cargo may then need a long truck leg to its final city.
Port-to-port vs door-to-door: where the extra days hide
A carrier counts days from loading at one port to discharge at another. Your business counts days from "goods ready at the factory" to "goods in my warehouse". The difference is usually one to three weeks.
Ship4wd, a digital forwarder, shows it clearly for Shanghai to Los Angeles. A full container (FCL) from China takes 14 to 20 days port to port, but 20 to 35 days door to door. A shared container (LCL) takes 15 to 25 days port to port and 22 to 35 days door to door.
The extra days come from five steps around the sea leg:
Factory to port and cut-off: cargo must reach the terminal before the carrier's cut-off. In the 16/11/2026 schedule, cut-offs fell about 3 to 10 days before departure.
Waiting for the sailing: most services sail weekly. Miss a cut-off and you wait for the next ship.
Consolidation: LCL cargo waits to be packed with other shipments. OVRSEA says LCL "typically adds 7 to 15 days" to FCL transit on China-Europe lanes.
Port and customs: discharge, documents, inspection and duty payment. Egypt's customs head said average sea clearance fell to 5.60 days at the start of 2025.
Final delivery: trucking or rail from port to warehouse, plus booking a delivery slot.
The land legs in the chart are TRG planning assumptions: 5 days to port, 3 waiting, 4 at the destination port and 2 for delivery. These are indicative, not promises. Replace them with your forwarder's numbers for your factory and your city.
📌 Note: Incoterms change who controls these days. On FOB, the supplier handles the origin legs; on DDP, the supplier handles almost everything. Our step-by-step guide to importing from China shows where shipping fits in the whole order.
Fees and rules change often. Get the TRG Importer Brief: one short email a week with changes that affect importers.
Air freight, express courier and rail transit times
When sea is too slow, you have three faster options. Each has its own definition of "transit time", so compare like with like.
1. Express courier: 1 to 5 business days
FedEx says International Priority delivers "typically in 1, 2, or 3 business days". International Economy takes "typically 2 to 5 business days". Express is door to door, and the courier usually handles customs clearance for you.
Business days exclude weekends and public holidays, so a "3-day" parcel sent on Thursday may land the next Tuesday. Our DHL, FedEx and UPS express guide covers surcharges and weight limits.
2. Air freight: about 4 to 7 days, plus clearance
Forto puts China-Europe air freight at 4 to 7 days. Ship4wd lists 5 to 7 days for standard air freight from Shanghai to Los Angeles. Air freight usually ends at the airport, so add import clearance and the truck to your door.
3. Rail to Europe: about 14 to 25 days
Forto quotes 14 to 25 days for China-Europe rail, depending on the route. Xinhua reported on 22/10/2026 that Xi'an to Duisburg takes "as little as 11 days, down from 15". Rail sits between air and sea on both time and price.
Read the chart with care: express days are business days, the other bars are calendar days. Use it to shortlist modes, then ask for dated quotes.
Shipping delays in 2026: Red Sea, Strait of Hormuz and late ships
Three forces moved sea transit times in 2026. Each one hits different lanes, so check the one that matters for your route.
1. Red Sea and Suez: a partial return
For a long time, many carriers sailed around the Cape of Good Hope to avoid the Red Sea. Forto says that diversion added an estimated 10 to 15 days. In late 2026, ships are moving back. Alphaliner data quoted by Ti Insight showed 63.00% of Far East to Europe capacity on Suez services, between 15/09/2026 and 15/10/2026.
The return is still in progress. On 16/11/2026, gCaptain reported that Maersk and Hapag-Lloyd will move three Gemini services back to Suez. AE2 starts on 04/12/2026, AE3 on 20/12/2026 and AE1 on 14/01/2027. Until your service switches, its old Cape timetable still applies.
2. Strait of Hormuz: disrupted since 28/02/2026
Shipping through the Strait of Hormuz has been disrupted since the US and Israel struck Iran on 28/02/2026. A UKMTO report quoted by Gulf News on 10/11/2026 put traffic about 65.00% below pre-conflict levels. Ti Insight noted that the IMF assumes Hormuz will not reopen until March 2027.
Maersk's update of 12/11/2026 names Khor Fakkan as its main UAE gateway, with Jebel Ali dry cargo via a land bridge. Bookings to Dammam, Al Jubail and Iraq are suspended. Maersk warns that "customers may experience longer transit and delivery times". It also charges a USD 1,000.00 fee per container for any vessel crossing the Strait.
3. Late ships everywhere
Sea-Intelligence measures how many ships arrive on schedule. In September 2026, only 50.60% of vessels arrived on time. Late vessels were 6.65 days late on average. That is why the worked example below adds a 7-day buffer to every sea plan.
📌 Note: Red Sea and Hormuz rules change weekly. Before you book, read your carrier's latest advisory and ask your forwarder to confirm the routing in writing. A quote without a routing is not a transit time.
Chinese New Year 2027 and other seasonal delays
China's State Council has fixed the 2027 Spring Festival holiday. It runs from Friday 05/02/2027 to Saturday 13/02/2027, nine days in total. Sunday 31/01/2027 and Sunday 14/02/2027 are make-up working days.
The official dates are only the core, because workers travel home early and return late. SEKO Logistics advises booking freight "at least three weeks ahead of shipment readiness". It also suggests adding one to two weeks to ocean transit plans around the holiday.
SEKO expects many factories to run with reduced staff into March 2027. Goods finished just before the holiday are the safest bet; goods "almost ready" on 04/02 may not move until late February. Our Chinese New Year 2027 production calendar gives the week-by-week plan.
Other dates slow shipping too. China's National Day holiday runs from 01/10 to 07/10 in 2027, and many factories pause for the whole week. Busy months before Western holiday sales also fill ships. Your own country's holidays matter as well, because customs brokers and warehouses close.
How to plan order dates backwards from your in-stock date
Do not plan forward from "order placed". Plan backwards from the day you need the goods. Each step subtracts days, and any step that lands on a holiday must move.
1. Fix the in-stock date
Choose the date the goods must be in your warehouse, ready to sell.
2. Subtract the destination legs
Take off customs clearance, port handling and delivery. Ask your customs broker for typical days at your port.
3. Subtract a delay buffer
Late ships averaged 6.65 days in September 2026. A 7-day buffer covers an average delay. Add more for Hormuz-affected lanes.
4. Subtract the slow end of the sea range
Use the slowest carrier average on your lane, not the fastest sailing. On Yantian to Rotterdam, that is 48 days.
5. Subtract the origin legs and production
Take off the cut-off, the trip to port, the pre-shipment inspection and the production time. The result is your last safe order date.
Here is the method on a real calendar. Example: a Rotterdam-area homeware importer buys from a Shenzhen factory and needs stock in its warehouse by 15/04/2027. The numbers below are a labelled example with TRG planning assumptions.
| Line | Step (example) | Maths | Date |
|---|---|---|---|
| 1 | Target in warehouse | given | 15/04/2027 |
| 2 | Latest discharge at Rotterdam | 15/04 minus 5 days (customs and delivery) | 10/04/2027 |
| 3 | Scheduled arrival with buffer | 10/04 minus 7 days | 03/04/2027 |
| 4 | Latest sailing from Yantian | 03/04 minus 48 days (slowest carrier average) | 14/02/2027 |
| 5 | Cargo cut-off at port | 14/02 minus 5 days | 09/02/2027: inside the holiday |
| 6 | Re-plan: goods ready, inspection next day | production finished before the holiday | 25/01/2027 and 26/01/2027 |
| 7 | Cut-off and sailing | cut-off Friday, vessel sails Tuesday | 29/01/2027 and 02/02/2027 |
| 8 | Worst-case arrival in warehouse | 02/02 + 48 days = 22/03; + 7 = 29/03; + 5 = 03/04 | 03/04/2027 |
| 9 | Spare days before target | 15/04 minus 03/04 | 12 days |
| 10 | Last order and deposit date | 25/01 minus 35 days of production | 21/12/2026 |
The backward count gives a sailing on 14/02/2027. But the cut-off would fall on 09/02/2027, in the middle of the holiday. The only safe plan is to sail before the holiday and accept 12 days of spare time. If the deposit is paid after 21/12/2026, the importer should move the target date or switch part of the order to rail or air.
Which shipping mode meets your deadline?
Once you know how many days you have between "goods ready" and "goods needed", the choice narrows quickly. The decision tree below gives a first answer. Weight, value and product rules can still change it.
Batteries, liquids and magnets may be refused by express or air. Large, cheap goods rarely justify air; order earlier, or split the shipment with a small urgent batch.
What goes wrong in practice with transit times
Most late shipments are caused by a gap nobody planned for, not by a slow ship.
1. The quote was port to port, the promise was door to door
A forwarder quotes "18 days"; cut-off, customs and delivery then add ten more. Fix: ask every forwarder for door-to-door days, broken down by leg.
2. "Ready" goods were not ready
Packing, labels or the inspection are not done, so the box misses the cut-off. Fix: book the inspection for the "ready" date and only confirm the booking after it passes.
3. The service changed its routing
A carrier moves a service to Suez, or drops a port call because of Hormuz. Fix: track the vessel, not just the booking, and re-check advisories weekly.
4. Transshipment at a hub
The box is discharged at a hub and waits for a feeder ship to Tunisia, Morocco or Egypt. A planned two-day connection becomes ten. Fix: ask whether the service is direct, and which hub it uses.
5. The holiday was planned at the wrong end
The buyer avoided sailing during Chinese New Year but forgot that production stops weeks earlier. Fix: put the holiday on the production plan, not only on the shipping plan.
If a shipment is already late, get the new arrival date in writing and warn your customer early. Cover the gap with a small air or express batch.
By region: MENA, Europe and UK, USA
MENA: Gulf lanes depend on the Hormuz situation, so read the latest Maersk Middle East operational update before booking. Morocco, Tunisia and Egypt are often served via Mediterranean hubs; check the routing with the Tanger Med port authority network for Moroccan cargo.
Europe and UK: sea transit depends on whether your service uses Suez or the Cape. EU arrivals also need a safety and security declaration in ICS2, the EU's import control system. Rail is a real middle option for inland Europe.
USA: the West Coast is the fast lane; the East Coast takes about one to three weeks more by water. Ocean cargo needs an Importer Security Filing with US Customs and Border Protection, so share supplier data early.
Shipping time checklist before you place the order
Related guides
Sea vs Air Freight from China (2026): Break-Even by kg, CBM
17 min read
ShippingChina Europe Rail Freight 2026: Route Map, 12-25 Days, Rates
17 min read
ShippingExpress Courier from China: DHL vs FedEx vs UPS (2026)
17 min read
Free toolSetup Route Finder: which company and bank fit you?
7 questions, 2 minutes
Glossary
Port to port: time from loading on the ship at the origin port to discharge at the destination port.
Door to door: time from collection at the factory to delivery at your warehouse, including both customs steps.
Cut-off: the last date and time cargo or documents can reach the terminal for a given sailing.
FCL / LCL: full container load (one shipper per box) and less than container load (shared box).
Transshipment: moving a container from one ship to another at a hub port on the way.
Schedule reliability: the share of vessels that arrive within the published schedule window.
FAQ
How long does shipping from China take by sea?
About 16 to 19 days to the US West Coast and 26 to 40 days to New York, port to port. North Europe averaged 38 days and Valencia 42 days in 2026 tracking data. Door to door adds one to three weeks.
How long does air freight from China take?
Usually 4 to 7 days, based on Forto and Ship4wd ranges. That is mostly airport based, so add clearance and delivery.
How long does express shipping from China take?
FedEx International Priority typically takes 1 to 3 business days, and International Economy 2 to 5. Customs checks can add time.
Why is shipping from China to Europe slower than to the US?
The distance is longer, and many services sailed around Africa to avoid the Red Sea. Some are returning to Suez in late 2026.
Is shipping to the Gulf delayed in 2026?
Yes, for ports inside the Strait of Hormuz. Traffic was about 65.00% below pre-conflict levels on 10/11/2026, and some carriers have suspended bookings to Dammam and Iraq.
How long does LCL take compared with FCL?
LCL usually takes longer because cargo waits to be consolidated and unpacked. OVRSEA says it typically adds 7 to 15 days on China-Europe lanes.
When should I order before Chinese New Year 2027?
Aim to have goods finished and inspected before late January 2027. The holiday runs 05/02 to 13/02/2027, and many factories slow down earlier.
How can I make shipping from China faster?
Book a direct service from the nearest big port, and finish the inspection before the cut-off. For urgent stock, send a small batch by air.
This guide is general information for importers. It is not legal, tax or financial advice. Transit times, routings and carrier advisories change often; confirm them with your carrier, forwarder or customs broker before you act.
Sources
25 official and provider pages, each with the date we checked it
ShipsGo Service Finder: Shanghai port routes and transit times (checked 18/11/2026)
ShipsGo Service Finder: Long Beach port routes and transit times (checked 18/11/2026)
ShipsGo Service Finder: Rotterdam port routes and transit times (checked 18/11/2026)
ShipsGo Service Finder: Port Said routes and transit times (checked 18/11/2026)
Yunxi Logistics: China-US sailing schedule, carrier listings of 16/11/2026 (checked 18/11/2026)
Goodhope Freight: China to Morocco freight log 2026, indicative transit (checked 18/11/2026)
Goodhope Freight: China to Tunisia freight log 2026, indicative transit (checked 18/11/2026)
Goodhope Freight: China to Egypt sea freight 2026, indicative transit (checked 18/11/2026)
Goodhope Freight: China to UAE freight 2026, indicative transit (checked 18/11/2026)
Ship4wd: shipping from Shanghai to Los Angeles (checked 18/11/2026)
Forto: shipping from China to Europe in 2026, sea, rail and air (checked 18/11/2026)
FedEx: compare international shipping options (checked 18/11/2026)
Xinhua: China-Europe freight trains, 22/10/2026 (checked 18/11/2026)
EnterpriseAM: Egypt's Customs Authority head on clearance times (checked 18/11/2026)
Sea-Intelligence: global schedule reliability, September 2026 (checked 18/11/2026)
gCaptain: Maersk and Hapag-Lloyd expand Suez Canal return, 16/11/2026 (checked 18/11/2026)
Ti Insight: Middle East and North Africa logistics monitor, October 2026 (checked 18/11/2026)
gCaptain: US and Israel launch attacks on Iran, 28/02/2026 (checked 18/11/2026)
Gulf News: Hormuz shipping below normal but not stalled, UKMTO, 10/11/2026 (checked 18/11/2026)
Maersk: Middle East operational update 54, 12/11/2026 (checked 18/11/2026)
State Council of China: 2027 public holiday arrangements (checked 18/11/2026)
SEKO Logistics: shipping from China to UK, Lunar New Year 2027 (checked 18/11/2026)
European Commission: Import Control System 2 (checked 18/11/2026)
US Customs and Border Protection: Importer Security Filing 10+2 (checked 18/11/2026)